Hierarchy Level Overrides
Scheduling properties set up in the Hierarchy Level Overrides tab of the Edit Schedule Settings window apply at the ROW (pipeline) level. Some scheduling properties inherit settings from those previously set up in the Time Between Survey Settings tab and ROW and Facility Settings. Inherited settings changed at the ROW level override and have precedent over those in the Time Between Survey Settings tab and ROW and Facility Settings.
Complete the following steps to set up scheduling properties at the ROW level:
-
Click Data Entry > Edit Schedule Settings and then the Hierarchy Level Overrides tab.
Hierarchy Level Overrides
-
Select the facility type you want to work with:
-
To select a facility type theme, select a theme from the Facility Types drop-down list.
-
To select multiple facility types, click the Ad Hoc Theme radio button and then select one or more facility types, such as Test Point, Rectifier, or Foreign Bond.
An Ad Hoc Theme only applies to the current session and is not saved. A facility type is selected when a check mark appears inside the check box. To clear the check mark, click the check box again.
-
-
Select the ROW(s) you want to work with by clicking the check box for each ROW in the middle pane of the Hierarchy Level Overrides tab.
ROW Selection(s)
-
Refer to the following table for a description of scheduling properties that apply at the ROW level and how to set up each of these.
Certain property names in the following table include an asterisk (*). The asterisk identifies scheduling properties you can set at the ROW level that will override and take precedent over those in ROW and Facility Settings and Time Between Survey Settings tab.
Property Name |
Property Description |
---|---|
Selected |
Include or exclude schedule settings at the ROW level when generating a schedule with facilities due for inspection. To include or exclude schedule settings, click Selected to display a drop-down arrow and select one of the following options in the drop-down list:
Selected Drop-down List
|
Scheduling Type Name |
A named set of schedule settings for a facility type created in the Schedule Type Settings tab. For information about how to create a Scheduling Type Name, refer to Schedule Type Settings. |
Due Date Calculation Method |
Shows the property setting inherited from Due Date Calculation Method column in the Schedule Type Settings tab. |
*Time Between Surveys |
Number of months or years between inspections. To set the time between surveys:
|
*Target Month |
Refers to the first survey month. Options in the selection list are based on the Time Between Survey value. As an example, if Time Between Surveys is 2 months, and the Target Month (first survey month) is January, surveys are set at 2-month intervals beginning in January. The next survey is due in March, the next in May, and so on. To set the target month:
|
*Target Year |
Refers to the first survey year when Time Between Surveys is more than 12 months. To set the target year:
|
*Grace Period / *Grace Period Unit |
Refers to a period of time in days or months an inspection can be late without incurring a compliance violation. To set a grace period for a scheduling type listed in Scheduling Type Name:
|
*Early Survey Limit Days |
Refers to how early an inspection can occur before the actual due date and still count as an inspection for the survey period. To set an early survey limit for a scheduling type listed in Scheduling Type Name, enter the number of days in the Early Survey Limit Days field. |