Scheduling properties set up in Hierarchy Level Overrides apply at the ROW (pipeline) level. Some scheduling properties inherit settings from those previously set up in Time Between Survey Settings and ROW and Facility Settings. Inherited settings changed at the ROW level override and have precedent over those in the Time Between Survey Settings and ROW and Facility Settings.
To set up scheduling properties at the ROW level, follow these steps:
Click the Select ROWs button to open the Select ROWs window. Select one or more pipeline segments by clicking the check box for each pipeline segment (Select ROWs). Click
Save to close the Select ROWs window.
Click Data Entry > Edit Schedule Settings > Hierarchy Level Overrides tab (Hierarchy Level Overrides).
Select the facility type(s) you want to work with by selecting a facility type theme or setting up an Ad Hoc Theme in Facility Types. See Facility Type Theme Option or Ad Hoc Theme Option.
Select the ROW(s) you want to work with by clicking the check box for each ROW in the middle pane of the Hierarchy Level Overrides window (ROW Selection(s)).
Refer to the following table for a description of scheduling properties that apply at the ROW level and how to set up each of these.
Certain property names in the following table include an asterisk (*). The asterisk identifies scheduling properties you can set at the ROW level that will override and take precedent over those in ROW and Facility Settings and Time Between Survey Setting
Property Name |
Property Description |
---|---|
Selected |
Include or exclude schedule settings at the ROW level when generating a schedule with facilities due for inspection. To include or exclude schedule settings, click Selected to display a drop down arrow and select one of the following options in the drop-down list:
|
Scheduling Type Name |
A named set of schedule settings for a facility type created in the Schedule Type Settings tab. |
Due Date Calculation Method |
Shows the property setting inherited from Due Date Calculation Method in the Schedule Type Settings tab. |
*Time Between Surveys |
Number of months or years between inspections. To set the time between surveys:
|
*Target Month |
Refers to the first survey month. Options in the selection list are based on the Time Between Survey value. As an example, if Time Between Surveys is 2 months and the Target Month (first survey month) is January, surveys are set at 2 month intervals beginning in January. The next survey is due in March, the next in May, and so on. To set the target month:
|
*Target Year |
Refers to the first survey year when Time Between Surveys is more than 12 months. To set the target year:
|
*Grace Period / *Grace Period Unit |
Refers to a period of time in days or months an inspection can be late without incurring a compliance violation. To set a grace period for a scheduling type listed in Scheduling Type Name:
|
*Early Survey Limit Days |
Refers to how early an inspection can occur before the actual due date and still count as an inspection for the survey period. To set an early survey limit for a scheduling type listed in Scheduling Type Name:
|