The following table identifies the fields required for recording pipeline current values.
Facility & Current Type |
Description |
---|---|
Pipeline Current: |
Add the following fields in the Test Point Information grid and "activate" fields for use.
Add the following fields in the Test Point Inspection grid:
|
Pipeline Insulator Current: |
Add the following fields in the Test Point Information grid and "activate" fields for use.
Add the field Insulator Current (Amps) in the Test Point Inspection grid. Use the field Insulator Current (Amps) to enter the amps value of the insulator shunt reading. PCS uses the reading and the value in the field Insulator Shunt Rating (mV/A) to calculate and enter a value in the field Insulator Shunt Factor (A/mV). |
Pipeline Insulator P/S |
|
Pipeline Galvanic Current: |
Add the following fields in the Galvanic Anode Information grid and "activate" fields for use.
Add the field Galvanic Current (Amps) in the Galvanic Anodes Inspection grid. Use the field Galvanic Anode Current (Amps) to enter the amps value of the galvanic anode shunt reading. PCS uses the reading and the value in the field Galvanic Anode Shunt Rating (mV/A) to calculate and enter a value in the field Galvanic Anode Shunt Factor (A/mV). |